There are two common scenarios for wanting to update a bid:

  1. The bid was submitted/received in a format not recognized by Planyard (i.e. pdf)
    This is usually the case when the whole bid total is 0

  2. For some reason, the price or volume should be updated (i.e. after negotiation)

Updating the bid

  1. Hover on the editable cell with your cursor

  2. Click on the pencil icon

  3. Update the data

  4. Click Save

Now the bid row is updated. NB! The updated cell is highlighted as yellow.

Did this answer your question?